PBIP Budget expenditure guidance
Cost Heading | Description |
---|---|
Land Acquisition | Applicants must be able to prove that the purchase price does not exceed the market value. Please indicate clearly the date the land was acquired and provide evidence as an enclosure to the application form. |
Premises Acquisition | Where purchase of premises is an essential element of a project, eligible expenditure is limited to the market value. Applicants must be able to prove that the purchase price does not exceed the market value. The premises must not have been in receipt of a national/EC grant within the previous 10 years. Please indicate clearly the date the premises were acquired and provide evidence as an enclosure to the application form.
|
Pre-Contract Professional Fees (does not include feasibility studies) And Contract Implementation Fees | Pre-contract works including design, bills of quantity and tender preparation. This does not include feasibility studies. Project management and supervision associated with the implementation of the project works, including Clerk of Works. Note:
East Renfrewshire Council applicants should ensure that all design costs have been incorporated including Property and Technical Services fees. |
Site Investigation | This should take account of specialist investigations required to identify contamination and recommend particular treatments etc. |
Site Decontamination | Specialist treatments to clear a site of particular contamination and dangers. |
Site Preparation/Clearance | This should include demolition works and the general preparation of sites, which is not part of specialist decontamination works. |
Preliminaries | As detailed in the Bill of Quantity |
Internal Services | This should include the provision of services/utilities within a building such as heating, lighting, plumbing and telecommunications |
Specialist Treatments | This should cover any specialist treatments not included under other headings such as :
Note: Applicants should specify the type of treatment(s) in an appendix. If treatments are associated with listed buildings they should be in accordance with the guidelines set down by Historic Scotland. |
Main Building Contract Work | This may include the following elements of work:
|
Main Environmental Contract Work | This may include the following elements of work:
|
Contingencies | Contingencies are an acceptable and reasonable cost at application stage. Note:
|
Security Provision | This should include eligible security provision, which will ensure the success of the wider project. |
Moveable Infrastructure (Fixture and Fittings) | Fixtures and fittings are only eligible if they are purchased for and used specifically for the project for example:
|